Measure Q

Dunlap Hall during renovations

Dunlap Hall Renovation

Project Summary:

  • Renovate and replace the aging guard rails around the pedestrian walkways on all levels of Dunlap Hall, as well as, providing a new elevator and stair tower.
  • Remodel the existing restrooms.

Current Status:

  • Construction began in April 2014 with a target completion expected at the end of September 2015.
  • Current activities include installation and erection of structural steel.
  • Upcoming activities include installation of exterior guardrail system and interior drywall system.
  • This project is delayed due to delays on fabrication of structural steel and discovery of unforeseen roof leaks.
  • The roof will need to be replaced following the renovation of work and completed under another contract for work.

Budget: $17.22 million